Florida Central is expecting their third and final continuous welded rail train for the SIS project this evening.
Florida Central is expecting their third and final continuous welded rail train for the SIS project this evening. The plan for unloading in Lake County on Thursday 11/21/13 is as follows:
9:30 AM – Rail train will backed between its storage location at Clay Blvd and stop short of Lakeshore Drive, Eustis.
10:00 AM – Begin unloading between Lakeshore and Clay, may experience railroad crossing blockings up to 30 minutes at the following roads in Eustis:
• West Lemon (auto shop)
• West Ward
• West Woodward
• West Stevens Ave
• West Atwater
11:30 AM – Begin unloading between Clay Blvd to North Mt Homer, may experience railroad crossing blockage up to 15 minutes at the following roads in Eustis:
• North Mt Homer Road
• Huffstetler Drive
1:00 PM – Begin unloading between Huffstetler Drive and South Mt Homer, may experience railroad crossing blockage up to 15 minutes at the following roads in Eustis and Tavares:
• Huffstetler Drive
• Highway 441
• South Mt. Homer Road
2:30 PM – Begin unloading between South Mt Homer and Alfred Street, may experience railroad crossing blockage up to 15 minutes at the following roads in Tavares:
• Alfred Street
• East Main Street (near Train Depot)
4:00 PM – move train south for unloading in Orange County for 11/22/13.
For more information about this project, please email Dennis Maples at [email protected].
Sincerely,
Richard J. Hoon
Assistant to the City Manager / Community Relations
Address/Location
Eustis Police Department
51 East Norton Avenue
Eustis, FL 32726
Contact
Emergency: 9-1-1
Non-emergencies: 352-357-4121