<p>Even with the increased rain events, Hoffman Bros. and their sub-contractors continue their efforts to complete the Michigan Ave reconstruction project by the end of November 2016. The remaining work this week includes pouring of the concrete intersection and crosswalks at N. Ann Arbor and the approach at the bridge on the west end of the project. The contractors will also continue working on various items on N. Ann Arbor Street. <strong>Note: A significant change in traffic routes is scheduled to take place next, Friday, October 28th at 7am. N. Ann Arbor Street is scheduled to re-open next Friday and the intersection at Maple and Michigan is scheduled to be closed for two weeks. The closing of the Maple/Michigan intersection will obviously have a substantial impact on local traffic, especially during student drop-off and pick-up times. Additionally, Mills Street is scheduled to be closed for one week, beginning early Monday, October 24th. </strong></p>
<p><strong>Note:</strong> Trash pick-up for those residents and businesses located in the construction zone – Waste Management will continue to pick up trash as regularly scheduled, however, due to the construction there may be instances when your trash is not picked-up on the regular day. If this happens, Waste Management will be picking up the missed trash collection the next day. Additionally, if Waste Management is not able to pick up your trash/recycling as regularly scheduled City staff encourages folks to contact the Department of Public Works (DPW) with questions/comments at 429-5624.</p>
<p>The City of Saline is selling pieces of the old street car tracks on a first come first served basis at City Hall, for those folks that would like to own a piece of Saline history. The cost is $25 for a 12” section of track; a portion of the proceeds will be used to pay for the cost of cutting up the track with the balance going towards a fundraiser to assist in paying for the new downtown streetscape.</p>
<p><strong><u>Week of October 24th: </u></strong><br />
<br />
<strong>Traffic Information</strong><br />
The following streets are scheduled to remain open this coming week: Harris, Davenport and Lewis. </p>
<p>N. Ann Arbor Street is scheduled to re-open Friday, October 28th. Maple is scheduled to close Friday, October 28th for two weeks. Mills Street is scheduled to close on Monday, October 24th for one week.</p>
<p><strong>Note: Downtown Parking Lot #1 (NE quadrant of downtown) has limited access from Hall Street until the new drive approaches at N. Ann Arbor Street are completed. </strong></p>
<p>City staff encourages everyone to slow down, be patient and obey the traffic signs. In addition, please do not take short-cuts through private property in an attempt to avoid the current traffic shifts/detour routes, as it is illegal and unsafe. And please pause to let people out of their driveways. </p>
<p><strong>Pedestrian Traffic</strong><br />
Temporary access has been installed to businesses on N. Ann Arbor Street. Sidewalk replacement continues to progress this week on the north half of the project.</p>
<p>There are parts of the construction zone that are not open to pedestrian traffic. There are also signs designating alternate pedestrian routes throughout the construction zone. Please obey the signs and seek alternate pedestrian routes that don’t include walking down the middle of re-routed traffic lanes.</p>
<p><strong>Construction Activities </strong></p>
<p>Fine grading in preparation for paving from Monroe Street west to the bridge this coming week.</p>
<p>Asphalt paving from Maple west where it is needed is scheduled for next Thursday and Friday. </p>
<p>More concrete curb & gutter and other concrete flat work is planned.</p>
<p>The decorative brick crew is scheduled to continue their work at various locations within the construction zone. </p>
<p>The street light and traffic signal crew will continue with the installation of light pole bases and conduit. Crews will also begin pulling wire and standing light poles this coming week.</p>
<p>Please stay tuned for updates as the Michigan Ave project progresses. The City of Saline staff will be providing a minimum of a weekly update and sometimes daily informational postings depending on what is taking place in the construction zone.</p>
Address/Location
City of Saline, MI
100 N Harris St
Saline, MI 48176
Contact
Emergency: 9-1-1
Non-emergencies: 734-429-4907
Todd Campbell
City Manager
[email protected]
734-429-4907