Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Downey Police Department
Monday August 28th, 2017 :: 10:12 a.m. PDT

Community

I-5 Corridor Improvement Project

Week of August 27, 2017



FLORENCE AVENUE INTERCHANGE PROJECT
On Thursday night, Aug. 31 crews plan to pour the bridge deck of the new half of the Florence Avenue bridge. This activity will require the full closure of northbound and southbound I-5 at Florence Avenue, as well as the closure of Florence Avenue bridge at I-5. This work is not expected to be particularly loud, but will include concrete trucks, truck back-up alarms, construction lighting and equipment staged within the lanes of I-5, south of Florence Ave. bridge.

The following closures are planned Thursday night, Aug. 31, to allow crews to complete this work:
• Northbound I-5 will be closed between Norwalk Boulevard and I-605 from 11:59 p.m. Thursday, Aug. 31 to 5 a.m., Friday, Sept. 1.
DETOUR: Motorists will exit northbound I-5 at Norwalk Boulevard off-ramp, turn left on Norwalk Boulevard, turn right on Firestone Boulevard and proceed to the northbound I-605 on-ramp; then transition onto northbound I-5.

• Southbound I-5 will be closed between I-605 and Norwalk Boulevard, from 11 p.m. Thursday, Aug. 31 to 5 a.m. Friday, Sept. 1. DETOUR: Motorists will be directed onto SB I-605 to exit Firestone Boulevard, east on Firestone Boulevard, east on Imperial Highway, south on Southbound Frontage Road to access the southbound I-5 on-ramp.
• Northbound I-605 Connector to Southbound I-5 closed from 9 p.m. Thursday, Aug. 31 to 6 a.m. Friday, Sept. 1.
DETOUR: Motorists will exit NB I-605 at Imperial Hwy. off-ramp, east on Imperial Hwy., south on SB Frontage Rd. to access SB I-5 on-ramp
• Southbound I-605 Connector to Southbound I-5 closed from 9 p.m. Thursday, Aug. 31 to 6 a.m. Friday, Sept. 1.
DETOUR: Motorists will continue on SB I-605, exit Firestone Blvd. off-ramp, east on Firestone Blvd., east on Imperial Hwy., south on SB Frontage Rd. to access SB I-5 on-ramp



• Florence Avenue will be closed between Orr & Day Road and Studebaker Avenue from 9:30 p.m. Thursday, Aug. 31 to 6 a.m. Friday, Sept. 1. Alternate routes for Florence Avenue are shown on the map below.


A portion of the sidewalk on Longworth Avenue, adjacent to the northbound I-5, has been closed to accommodate sound wall reconstruction. A chain link fence has been installed to close this area of the sidewalk from public access through the end of 2017. Crews have begun removing this portion of the sidewalk and the adjoining block wall, as they prepare to reconstruct the freeway sound wall at this location. This work is currently on hold and will resume soon. Once work resumes, sidewalk/block wall removal work will take place weekdays between 7 a.m. and 3:30 p.m. and may be intermittently loud and disruptive due to concrete removal activities. The sidewalk will be restored once sound wall construction is complete.

IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT
Sunday, Aug. 27 through Thursday, Aug. 31, the contractor will be performing falsework operations nightly between 9 p.m. and 6 a.m. and will close southbound Pioneer Boulevard to traffic between Crewe Street and Imperial Highway.

In addition, on Sunday, Aug. 27 through Thursday, Aug. 31, Imperial Highway will be closed nightly from 9 p.m. to 6 a.m., between Adoree Street and South Frontage Road, for shoring and drilling operations for CIDH (cast in drilled hole piles).

On Tuesday, Aug. 29 between 8:30 p.m. and 6 a.m., Imperial Highway will be closed between Adoree Street and South Frontage Road for concrete operations.

Closure areas are shown in red on the maps below; detour routes are highlighted in green. Unless otherwise noted, work will be performed between 9 p.m. and 6 a.m.



This information can also be found on the project Google map.

Pile driving activity along I-5 at Pioneer Boulevard and Imperial Highway is ongoing; this work will be conducted weekdays between 7 a.m. and 3:30 p.m. and will be ongoing intermittently for approximately four more weeks. Please be advised this work may be loud and disruptive due to equipment noise, vibration, and pounding related to pile driving activity.

As crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard bridges at I-5, one lane in each direction will be closed on each street (at I-5) during the daytime, between 8:30 a.m. and 3:30 p.m.

ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT
On Monday, Aug. 28, crews will resume nightly closures on Firestone Boulevard south, between Shoemaker Avenue and Carmenita Road (shown in red below), between 7 p.m. and 5 a.m., Mondays through Fridays, for approximately the next four weeks. The contractor will be performing nightly concrete pours throughout the project area and these closures are necessary to allow for construction vehicle staging and to maintain nightly access for the contractor to their concrete plant.
.
Flaggers will be on site to maintain access for businesses within the closure area shown below in red. However there will be no through access along this portion of Firestone Boulevard south for the general public. Available alternate routes are highlighted on the map below in blue.


This information can also be found on the project Google map.

Crews have begun work to reconstruct N. Firestone Boulevard, between the main entrance of Norwalk Village Mobile Home Park and Rosecrans Avenue. In order to reconstruct the street, the main driveway for the Norwalk Village Mobile Home Park will be closed to all traffic through fall 2017. While this driveway is closed, access to enter and exit the community will be maintained via the back driveway near the storage lot. There will be no through access to Rosecrans Avenue from N. Firestone Boulevard, while this work is being conducted. The closure area is shown on the map below in red; the detour route is shown in green.

VALLEY VIEW AVENUE INTERCHANGE PROJECT
On Wednesday morning, Aug. 30, crews will close the southbound Valley View Avenue left hand turn lane to S. Firestone Boulevard.
The left-turn lane will remain closed for approximately 18 months. Motorists will be detoured to head south on Artesia Boulevard to access the southbound I-5 freeway on-ramp
(shown in red on the map below; detour route highlighted in green).

Pile driving and shoring activities are ongoing on the south side of Valley View Avenue. This work will be conducted weekdays during the daytime between 7 a.m. and 3:30 p.m.


*DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.


For information regarding upcoming closures, detours and other construction activity, be sure to check out the project Google map. This map will be updated in real time, with the latest information regarding project construction. Click the image below to view the map.


I-5 HOV Interchange Improvement Projects, (855) 454-6335, Los Angeles, CA 90012
SafeUnsubscribe™ [email protected]

Forward This Email to a Friend | Update Profile | About our service provider

Sent by [email protected] in collaboration with




Try it free today

Address/Location
Downey Police Department
10911 Brookshire Ave
Downey, CA 90241

Contact
Emergency: 9-1-1
Non-emergencies: 562-861-0771

Navigate & Discover