Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Chula Vista Office of Communications
Thursday April 19th, 2018 :: 03:09 p.m. PDT

Community

South Bay Rapid Progress Report for Chula Vista

Here's the latest on the construction of the South Bay Rapid project in Chula Vista. For more details, go to www.KeepSanDiegoMoving.com/SouthBayRapid

Heritage Road to View Park Way (Segment 1B)
• Periodic lane closures in both directions along East Palomar Street between Heritage Road and Olympic Parkway for continued road work improvements.

Olympic Parkway to State Route 125 (SR 125) (Segment 2)
• Periodic noise, dust, and vibrations for the removal of the temporary sound blanket placed between the guideway bridge construction and the Monet and Treviana properties. Removal of the entire sound blanket is expected to take 6-8 weeks.
• Periodic noise, dust, and continuous closure of the left (No. 1) lane on eastbound East Palomar Street between Olympic Parkway and Magdalena Avenue for guideway construction.
• Periodic noise, dust, and lane closures along Olympic Parkway between La Media Road and SR 125 from 9 a.m. to 4 p.m. daily to accommodate installation of irrigation improvements.

Town Center Drive to Birch Road (Segment 2)
• Periodic daytime noise and dust along Eastlake Parkway adjacent to Kestrel Falls Road while crews continue future Otay Ranch Rapid Station platform work.

Address/Location
Chula Vista Office of Communications
276 4th Ave
Chula Vista, CA 91910

Contact
Emergency: 9-1-1

Navigate & Discover