Resurfacing of US 27 to begin July 17th
US 27 (10.5 – 14.9 mile-marker) – A resurfacing project is ready to begin on US 27 from Washington Street in Alexandra to Ripple Creek in Cold Spring.
Work will be done during NIGHTTIME hours starting at 8 p.m. until 6 a.m.
Starting July 10, traffic signal loops will be installed.
On July 15 and 16, the road will be milled and then the resurfacing will start on July 17.
If needed, some paving could possibly take place on Saturday, July 21. Work is weather dependent. Motorists should watch for lane closures, crews and equipment. Short delays are possible.