Winhall Culvert Replacement, Route 30 Information

Construction Update

Winhall Culvert Replacement, Route 30

DATE: Thursday, 7/11/19

PROJECT TYPE: Culvert Replacement Project

LOCATION: The culvert is located on VT Route 30 in Bondville, between the Stratton Mountain Access Road and West Hill Road.

Traffic Impacts: A 72-hour closure is scheduled for Friday, 7/19/19. The closure period will begin at 6:00pm on Friday and the road shall re-open prior to 6:00am Monday, 7/22/19 in order to allow the contractor full access to the roadway as spatial and resource constraints limit the available space to complete the work. A signed detour will be in effect utilizing Vermont Route 11 and Vermont Route 100.

ROUTE 30 WILL BE CLOSED JUST SOUTH OF THE STRATTON MOUNTAIN ACCESS ROAD BEGINNING FRIDAY, 7/19/19 AT 6:00 PM.

THE ROAD IS SCHEDULED TO REOPEN TO THROUGH-TRAFFIC

ON MONDAY, 7/22/19 BY 6:00 AM.

Construction Activities: Please see below for a correction of a misprint in the previous update.

The contractor plans to work on the water diversion system next week, preparing some sump areas so they have a dry place to work during the closure, and will begin work on the stream bed. Friday, 7/19 an alternating one way traffic pattern will be in place most of the day prior to the 6:00 PM closure.

Traffic will be detoured utilizing VT Route 11 and VT Route 100

WINHALL

STP SCRP(14)

Culvert rehabilitation on VT30, MM 0.28.

Work proposed for this project involves the removal and replacement of an existing 30-inch corrugated metal pipe culvert, which carries an unnamed stream under VT Route 30, with a concrete reinforced box culvert. The existing culvert invert has deteriorated and there are areas of separation along the length of the pipe.

A stone laid headwall at the outlet of the pipe has failed and fallen into the stream causing slope stability issues that are encroaching toward the shoulder of VT Route 30.

A 3-day closure is proposed within the timeframe of July 19th to July 29th to allow the contractor full access to the roadway as spatial and resource constraints limit the available space to complete the work. The closure period will begin at 6:00pm on a Friday and shall open prior to 6:00am the following Monday.

Traffic will be detoured utilizing VT Route 11 and VT Route 100.

Closures:
•VT-30 will be closed for 3 days between July 19, 2019 and July 29, 2019.

Contact Information

VTrans Project Manager
Bruce Martin
(802) 595-9653
[email protected]

VTrans Resident Engineer
Chad Greenwood
(802) 498-8253
[email protected]

Contact VTrans

Address/Location
Winhall Police & Rescue
113 Vermont Route 30
Bondville, VT 05340

Contact
Emergency: 9-1-1
Non-emergencies: 802-297-1013

Navigate & Discover