Advisory: Unforeseen problems, O&R’s target 4 complete road restoration/re-opening of Broad St. to 2-way traffic is 1-10-20
TRAFFIC ADVISORY: The following update is directly from the Rockland Electric Company.
PROJECT WORK PLAN – December 27h and beyond:
Despite a construction delay caused by contractor damage to a previously unmarked SUEZ water line on Dec. 14, principal construction on Broad St. was completed on Dec. 24. The secondary construction is proceeding around the clock with the target for completion on December 30. Post-construction road restoration is expected to take longer than originally planned. As the construction progressed, subsurface conditions changed. That will require additional work to make final restoration repairs to the roadway. Barring unforeseen developments, our target for complete road restoration and the re-opening of Broad St. to two-way traffic is Jan. 10.