2020 Residential Pav't Milling and Overlay Work Update

The City of Norton Shores wishes to update you that its contractor plans to place the top pavement course on the local streets starting Tuesday, August 24, 2020 (weather dependent).

Project Locations are as follows:
1. Carol Street, Sternberg to Getz
2. Davis Road, Hile to the north end
3. Hiawatha Drive, Seminole to Norton
4. Leif Avenue, Estes to Wickham

Work is scheduled to be completed prior to the end of the month.

Access and travel thru the affected streets will be limited for a short time during the work with traffic controlled by cones and flagging operations. Delays should be expected.