Advisory
If you have any questions please contact the Engineering Department at (209) 599-2108.
PG&E gas line construction to begin in October. Multiple lane closures and heavily impacted traffic to be expected.
From October through December 2020, PG&E will be performing work on gas lines at four intersections in Ripon.
There will be multiple lane closures and traffic is expected to be heavily impacted. Residents are encouraged to use alternative routes.
Below is a list of the locations and the dates construction will be performed.
Intersection Location | Hours of Construction | Dates of Construction | ||
W. Main St & Wilma Ave | 8:30AM – 5PM | 10/12 –10/30 | 11/30 – 12/4 | 12/7 - TBD |
Acacia Ave & Second St | 8:30AM – 5PM | 10/26 – 11/13 | 11/30 – 12/4 | 12/7 - TBD |
S. Stockton Ave & E Fourth St | 7AM – 5PM | 10/1 – 10/16 | 11/30 – 12/4 | 12/7 - TBD |
E Fourth St & S. Industrial Ave | 7AM – 5PM | 10/5 – 10/30 | 11/30 – 12/4 | 12/7 - TBD |
If you have any questions please contact the Engineering Department at (209) 599-2108.
Address/Location
City of Ripon, CA
259 N Wilma Ave
Ripon, CA 95366
Contact
Emergency: 9-1-1
Non-emergencies: 209-599-2108