Bi-weekly update on the East Blithedale Avenue Rehabilitation Project
Bi-weekly update on the East Blithedale Avenue Rehabilitation Project:
Important Notice:
Sunday, May 22, 2022, residents will hear jackhammering during the grinding of the asphalt between 7:00 PM and 10:00 PM. Noise mitigation will be performed to reduce the noise output.
On June 9, 2022, there will be no roadway closures project-wide to accommodate the school graduations.
Where: Argonaut is scheduled to grind and pave E. Blithedale Avenue from US 101 to Amicita Avenue and Ashford Avenue from Meadow Drive to Lomita Drive
When: May 22nd, 2022, through May 29, 2022. The work will be performed between the hours of 7:00 PM & 5:00 AM.
Traffic striping will also be installed during the overnight work hours from June 12, 2022, through June 23, 2022.
Residents should expect to feel vibrations from the grinding operation. Noise from jackhammering will be mitigated with the use of sound blankets to not exceed 80 dBA at a distance of 50 feet
Local residents may see additional lighting as light towers are necessary to safely perform this night work.
Please visit E. Blithedale Project for further information.
Project contact information:
Direct Project Contact Information 24/7: (628) 238-0221
[email protected]
Stay Up to Date on the DPW Twitter Site
Address/Location
Mill Valley Police Department (CA)
1 Hamilton Dr
Mill Valley, CA 94941