East Prospect St. business patrons may experience restricted access to and from parking/loading areas during the milling and paving operations. We will maintain business access to the greatest extent possible. Patrons may need to follow detours when no-thru traffic limits access. At times, parking in a business’s rear lot or off-site may be necessary.
Please keep in mind that inclement weather may delay construction. The Borough will provide daily updates on construction progress.
No Parking and construction/detour signs will be posted along the roadway at least 24 hours prior to the start of the milling and paving of the road. Access to the street will be limited until approximately 5:00 P.M. on days of construction.
08-01-2022 EAST PROSPECT STREET MILLING & PAVING UPDATE
Milling and paving schedule for East Prospect Street, from Franklin Turnpike to Rt. 17:
At approximately 5:00 pm East Prospect St will be open to all traffic for the remainder of 08-01.
On 08-02 East Prospect St from Franklin Tpk. to Centre Ave. will be open in both directions for local traffic only.
Day | Date | Operation | Details |
Monday | August 1st | Milling | Franklin Tpk. to Nordham St. COMPLETE |
Tuesday | August 2nd | Milling | Beginning at Nordham St, and ending at Rt. 17 |
Wednesday | August 3rd | Paving | Beginning at Franklin Tpk., ending between Richard Dr. and Nordham St. |
Thursday | August 4th | Paving | Beginning between Richard Dr. and Nordham St, ending at Rt. 17 |
East Prospect St. business patrons may experience restricted access to and from parking/loading areas during the milling and paving operations. We will maintain business access to the greatest extent possible. Patrons may need to follow detours when no-thru traffic limits access. At times, parking in a business’s rear lot or off-site may be necessary.
Please keep in mind that inclement weather may delay construction. The Borough will provide daily updates on construction progress.
No Parking and construction/detour signs will be posted along the roadway at least 24 hours prior to the start of the milling and paving of the road. Access to the street will be limited until approximately 5:00 P.M. on days of construction.