Update to Repair to the Donald and Bernice Watson Recreational Trail
Update - August 8, 2022
As of Monday, August 8, 2022, the repairs on the crosswalks at the intersections of the trail and Royal Oaks Dr. N. (East end), Royal Oaks Dr. N. (West end) have been completed. Given that Duarte Unified School District schools reopen this week and eastbound I-210 lane closure will take place August 17-23, repairs on the Mt. Olive and the Donald and Bernice Watson Recreational Trail crosswalk have been postponed to lessen traffic impacts to Duarte residents and visitors. A new date for the work will be announced on the City's website, social media and through the Nixle once that has been determined.
--------------------------------------------------------------------------------------------------
Original message:
Weather permitting and save any other delay, full and/or partial closure of the road have been scheduled for August 1 through August 12, 2022.
We will make every effort to allow as much access as possible during this repair. Please respect the signs posted for construction signs as those are placed for your safety. We thank you for your cooperation during the scheduled repairs and assure you we will move through the project as efficiently as possible to minimize any inconvenience.
ROYAL OAKS DR. N. (EAST SIDE)
Monday-Wednesday (8/1/22-8/3/22):
Removal and reconstruction of pedestrian crosswalk.
- Vehicle access will be restored by Thursday, August 4.
- Vehicles will be directed to use the west end of Royal Oaks Dr. N. during construction.
- Pedestrian access will be limited as deemed necessary for safety.
ROYAL OAKS DR. N. (WEST SIDE)
Thursday-Friday (8/4/22-8/5/22):
Removal and reconstruction of pedestrian crosswalk.
- Vehicle access will be restored by end of day Friday, August 5.
- Vehicles will be directed to use the east end of Royal Oaks Dr. N. during construction.
- Pedestrian access will be limited as deemed necessary for safety.
ROYAL OAKS AT MT. OLIVE DRIVE
Thursday-Friday (8/4/22-8/12/22):
Construction will be completed in three phases. Access to through traffic will remain open at all times with partial sections of the street lanes blocked.
For questions regarding this work you may contact the Community Development Department, Public Works Division, at (626) 357-7931 or by email at [email protected]
Address/Location
City of Duarte
1600 Huntington Dr
Duarte, CA 91030
Contact
Emergency: 9-1-1
Non-emergencies: 626-357-7931
TEXT-A-TIP - Text TIP DUARTE followed by your message, to 888777