Cohas Brook Sewer Project – Contract No. 4 – Week of August 29 – September 2
Park Construction Corporation will begin ‘base’ roadway paving in Bodwell Road from Pheasant Lane to the Londonderry town line during the week of August 29th thru September 2nd. The work will continue for approximately four days until completion. Temporary road lane closures will be required during certain stages of the work. Police details and flaggers will be on-hand to assist motorists. Bodwell Road will remain open to residents, local traffic, and emergency response vehicles during all aspects of construction.
Crew #1: (Park Construction Corporation and Continental Paving, Inc.) will grind/reclaim the existing pavement surface and gravel, re-grade the road, make driveway connections, and install new pavement.
Address/Location
Manchester, NH: City
Manchester, NH 03101
Contact
Emergency: 9-1-1