Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Manchester, NH: City
Friday August 26th, 2022 :: 03:27 p.m. EDT

Advisory

NIXLE Notice: Christian Brook Sewer Separation Contract 1 - Week of August 29 - September 2

P. Gioioso & Sons will continue work on North Street, Bay Street East Back and Myrtle Streets during the week of August 29th thru September 2nd.

Crew #1: Will perform spot sewer repairs on Bay Street East Back off North Street on Monday and on Myrtle Street off of Belmont Street on Tuesday. The crew will then return to North Street and start installation of water main piping between Walnut Street East Back and Beech Street.

Crew #2: Will start installing water main on North Street between Hemlock Street and Russell Street, then will resume installation of the 42-inch drainage piping including ledge removal on North Street between Russell Street and Hawthorn Street.

Crew #3:  (Advanced Drilling & Blasting) will perform drilling and blasting of ledge on North Street between Russell Street and Hawthorn Street, then move to the North Street and Ash Street intersection.

Crew #4: P. Gioioso & Sons paving crew will be on site to install asphalt paving on North Street between Walnut Street and Beech Street and on North Street between Hemlock Street and Russell Street. Temporary patches will also be paved on Walnut Street East Back.

In support of the Christian Brook sewer separation project, Liberty Utilities will be relocating the gas main on Beech Street at the North Street intersection.

If you have any questions, please feel free to contact the project team. 

Address/Location
Manchester, NH: City

Manchester, NH 03101

Contact
Emergency: 9-1-1