Work will be conducted each day between 6:00 am and 5:00 pm.
During milling, roadways will remain open for school busses, emergency vehicles, and residents that live within the project area.
During paving, roadways will be closed to all vehicles. It is recommended that during paving resident's park vehicles outside of the affected roadways prior to the 6:00 am start time.
The milling and paving schedule is subject to change. Updates will be provided daily.
09-19-2022 ROAD PAVING PROGRAM UPDATE - NEW SCHEDULE
Below is a list of the streets to be repaved along with the current schedule.
Order | Street | Section | Milling/Cleaning | Paving |
1 | Hemlock St | All | Complete | 9/20 |
1 | Evergreen St | All | Complete | 9/20 |
2 | Sherman Ave | Hopper Ave to/inc Cul De Sac | 9/20 | Projected 9/21 or 9/22 |
3 | Frederick St | Franklin Tpke to Harrison Ave | 9/20 | Projected 9/21 or 9/22 |
3 | Walter Nightengale Pl | Franklin Tpk to Hewson Ave | 9/20 | Projected 9/21 or 9/22 |
Work will be conducted each day between 6:00 am and 5:00 pm.
During milling, roadways will remain open for school busses, emergency vehicles, and residents that live within the project area.
During paving, roadways will be closed to all vehicles. It is recommended that during paving resident's park vehicles outside of the affected roadways prior to the 6:00 am start time.
The milling and paving schedule is subject to change. Updates will be provided daily.