Christian Brook Sewer Separation Contract 1 - Week of September 26 - September 30
P. Gioioso & Sons will continue work on North Street during the week of September 26th thru September 30th.
Crew #1: Will continue installation of 60” Drain piping on North Street between Ash Street and Maple Street.
Crew #2: Will continue installation of the 12” water main on North Street between Hawthorne Street and Linden Street, then resume installing catch basins on North Street between Russell Street and Linden Street.
Crew #3: (Advanced Drilling & Blasting) will continue drilling and blasting ledge on North Street between Ash Street and Maple Street then relocate and resume blasting on North Street starting at Linden Street working east towards Dallaire Street.
In support of the Christian Brook sewer separation project, Liberty Utilities will continue relocating the gas mains on Russell Street and Maple Street.