Manchester, NH: City
Friday October 7th, 2022 :: 02:16 p.m. EDT

Advisory

Christian Brook Sewer Separation Contract 1 - Week of October 11 - October 14

P. Gioioso & Sons will continue installation of drainage piping during the week of October 11th thru October 14th. There will be no work on Monday, October 10th, Columbus Day.

Crew #1: Will continue removal of ledge and installation of 60” Drain piping on North Street between Ash Street and Maple Street. Maple Street will be closed to traffic between Salmon Street and Webster Street during the beginning of the week as the Drain installation progresses up to the intersection. This crew will then make repairs to the sewer between Ash Street and Maple Street.

Crew #2: Will continue installation of manholes and drain piping on Dallaire Street.

Crew #3:  (Advanced Drilling & Blasting) will continue drilling and blasting ledge on North Street between Linden Street and Ashland Street.

If you have any questions, please feel free to contact the project team. 