Christian Brook Sewer Separation Contract 1 - Week of November 14 - November 18
P. Gioioso & Sons will continue installation of drainage and water piping during the week of November 14th thru November 18th
Crew #1: Will continue installation of the 42” Drain piping on North Street between Ashland Street and Dallaire Street, and continue prepping roadway subgrade for paving.
Crew #2: Will install two water services at the Hemlock Street intersection with North Street on Monday, install a new water gate valve on Maple Street on Tuesday, then resume preparing roadway subgrade for paving on Dallaire Street.
In support of the drain piping installation, Liberty Utilities and RH White will complete relocating the gas main on Maple Street at the North Street intersection.
Maple Street will be detoured around the North Street intersection during working hours starting on Wednesday to allow resumption of blasting and main line drain pipe installation.
Crew #3 will finish grade the prepared roadway subgrade and pave North Street starting at Russell Street and working towards Ashland Street. Dallaire Street will be paved between Salmon Street and North Street. As time permits, North Street between Beech Street East Back and Maple Street will be paved.
If you have any questions, please feel free to contact the project team.