Witherspoon Street Phase 1 Construction Update for the Week of February 27th - March 3rd (Princeton Engineering Dept.)

Week of February 27 - March 3, 2023*

  • Earle Asphalt Co will continue concrete sidewalk removal, curb and paver installation on the west side of Witherspoon Street between Nassau and Spring Street and on the east side of Witherspoon Street between Paul Robeson Place/Wiggins Street and Spring Street.
  • The sidewalk on the east side has opened up to pedestrians. Snow fence nearest the frontage of the businesses on the west side will remain in place until the paver installation is completed. Pedestrians will be rerouted to the nearest crosswalk or the opposite side while areas are blocked off during construction. Wooden planks will be available near business entrances to provide access for employees, patrons and deliveries.
  • A New temporary loading zone has been striped on Hulfish Street between Witherspoon Street and Palmer Square East, opposite Griggs Parking Lot. Business delivery trucks may continue to utilize designated loading zones and crosswalks. Stopping in the travel lane or blocking intersections to load or unload is prohibited.
  • Other available loading zones are on Nassau Street and Spring Street.
*This schedule is subject to change due to inclement weather or project delays and will be updated accordingly via this newsletter.

Traffic and Parking
  • Witherspoon Street is now a one-way street northbound. Upon construction completion, Witherspoon Street will reopen to traffic traveling northbound. The left (west) side of the white paver line is a 10-foot designated service lane. The right (east) side of the white paver line lane is the 10-foot travel lane. Stopping, Standing or Loading is not permitted in the active travel lane.
  • Periodically during construction, Witherspoon Street between Nassau Street and Spring Street, may experience a lane shift or temporary road closure to deliver material and equipment to the work area. Detour signage will be in place during those occurrences.
  • Metered parking spaces on Witherspoon Street between Hulfish Street and Paul Robeson Place/Wiggins Street are bagged during construction hours to allow for two lanes of traffic. Parking will be restored there on weekends. Metered parking spaces on Hulfish Street between Witherspoon Street and Palmer Square East will remain bagged until construction completion.
Waste Collection
  • New trash carts have been delivered for some residents on Witherspoon Street. Residents should use the new carts and place them in front of their building front on collection days.
  • Trash and Recycling collection for businesses on both the west and east side will take place in the designated area on Witherspoon just past the Spring Street Crosswalk. Do Not Block Traffic Signs with The Bins. 
  • Trash and Recycling collection for businesses near Nassau Street have made arrangements for collection on Nassau Street. Businesses whose collection is in Tulane Yard should be collected as normal.

Instructions:

Please be advised.

Address/Location
Princeton NJ Police Department
1 Valley Rd
Princeton, NJ 08542

Contact
Emergency: 9-1-1
Non-emergencies: 609-921-2100

Tiffany Smith
Engineering
[email protected]
609-751-1694

TEXT-A-TIP -  Text TIP PRINCETON followed by your message, to 888777

Submit an anonymous web tip

Alert Details

Severity:
Minor - Minimal to no known threat to life or property
Urgency:
Future - Responsive action SHOULD be taken in the near future
Certainty:
Observed - Determined to have occurred or to be ongoing
Category:
Utility, telecommunication, other non-transport infrastructure
Event:
Utility Emergency

Navigate & Discover