University Avenue Reconstruction Project Update
In order to construct the new pedestrian overpass structure at University Bay Drive, a detour of the multi-use path on the north side of University Avenue between Shorewood Boulevard and Highland Avenue is anticipated to begin on April 19, 2023. Electronic message signs will be placed on the path approximately three days before the detour is scheduled to begin. Detour signage will be installed to delineate the route throughout the duration of the detour. Note that the work is weather dependent and may be subject to change.
A map of the detour is available at: https://www.shorewood-hills.org/vertical/sites/%7B00D5AF3F-ADFE-4173-AF3A-FC0C1A78DA4B%7D/uploads/Multi-Use_Path_Detour_(Begins_4-19-23).pdf
For more information go to: https://www.cityofmadison.com/engineering/projects/university-avenue