Seng, Kunz , Aue, Pertie and Wilson Water Main Construction
Water main construction is scheduled to start at Seng and Kunz Roads between Hile and Eugene on August 22, 2023.
Work is currently scheduled to start on Aue east of Miller on September 6, 2023, and Petrie and Wilson west of Grand Haven Road on September 18, 2023.
All water main installation work is scheduled to be completed by November 30, 2023, with final restoration work done in the spring.
The streets will be closed except for local traffic. Access will be blocked for short durations to driveways during the installation in front of homes and delays should be expected. It is advised that traffic seek alternate routes around the work area.