Pascack Road Milling & Paving Update
Please take a moment to review the updated and projected milling and paving schedule for the Pascack Road resurfacing project. Please expect major detours and delays while work is conduced.
Milling Operations - 7:00am - 4:00pm
Monday 9/18 - Milling to Continue on Pascack Road starting in the area of the Knights of Columbus and ending just south of Linwood Avenue. Road closures can be expected in between Ridgewood Road and Soldier Hill Road.
Paving Operations - 7:00am - 5:00pm
*Residents located within the paving zone need to make arrangements to have their vehicles moved out of their driveways and onto a side street prior to the start of the work day at 7:00am. After hot asphalt is applied, NO VEHICLES can drive on the pavement for at least 60-90 minutes to allow for the asphalt to cool and harden.*
Tuesday 9/19 - Paving Pascack Road starting at Ell Road (Hillsdale Boarder) and continuing south until the area of Crest Place (past Memorial Field)
Wednesday 9/20 - Paving Pascack Road starting in the area of Crest Place until the area of Sutton Way (past the Shopping Center)
Thursday 9/21 - Paving Pascack from the area of Sutton Way until Linwood Avenue
Address/Location
Township of Washington
350 Hudson Ave
Township of Washington, NJ 07676
Contact
Emergency: 9-1-1
Non-emergencies: 201-664-4404