Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

City of Oneonta
Thursday May 2nd, 2024 :: 03:06 p.m. EDT

Advisory

River St and Ann St Reconstruction and Water Main Replacement project

This is an update to the River St and Ann St Reconstruction and Water Main Replacement project.  

Beginning Monday, May 6th at 7:00 am the contractor will begin MILLING and PAVING work. 

The tentative, weather permitting schedule is as follows:
Monday 5/6- milling from Main Street to Baker Street, both directions
Tuesday 5/7 - milling from Baker Street to Parish Avenue, both directions
Wednesday 5/8 – milling at all intersecting streets, plus Ann Street, both sides
Thursday and Friday 5/9 & 5/10 – paving 2 ½” binder asphalt layer, all areas
Monday thru Wednesday – 5/13 thru 5/ 15 paving 1 ½” top asphalt layer, all areas
 
Please avoid these areas if at all possible. SEEK ALTERNATE ROUTES and EXPECT LONG DELAYS.  Flaggers and one lane traffic will be in place in the work zones.   Temporary signage, lights and barricades will be in place.  Please exercise extreme caution and obey all flaggers, signs and barriers at all times.

The City will issue periodic project updates or changes via Nixle PSA as needed.

For questions or concerns related to this project, please contact the Department of Public Works by emailing [email protected], or calling 432-2100.

Address/Location
City of Oneonta
258 Main St
Oneonta, NY 13820

Contact
Emergency: 9-1-1
Non-emergencies: 607-432-6450

Submit an anonymous web tip

Navigate & Discover