PFAS Water Treatment Project Update: 5-7-24
All tanks have been delivered and installed at all the Well House locations. The next phase will include the delivery and installation of the filter media at each location. Once the filter media is installed, there is a series of testing that is required before the new treatment systems are officially turned on. After all the testing is completed and approved by the Department of Environmental Protection, our PFAS levels should be at a non-detectable level. The Water Treatment Project is scheduled to be completed by the end of July 2024. After the treatment systems are turned on and fully operational, we will begin working on the landscaping, fencing and cleanup at all the locations.
If you have any questions about the Water Treatment Project, please contact the Borough Administrator's Office at 201-652-5300 ext. 227.