Advisory

NYSEG - Gas Main Install - West St & Ravine - 9/16-9/20/24

NYSEG and it's contractor, DDS Companies will be installing a gas main this week, 9/16-9/20/24 on West Street & Ravine Parkway.  Please see information below provided by the contractor and attached map.  Please use caution and obey all temporary traffic control devices.

Here is the current plan for gas main installation and traffic impact. This week 9/16 – 9/20 there will be a single lane closure watched by flaggers on West St illustrated by the light blue line.
This is expected to last 1 week until moving down towards the Ravine Parkway intersection. Scheduled to start around Mon/Tues the area shown by the red line will be affected with a single lane closure on West St as well as 1 of the entrances to Ravine Parkway.  Only one will be closed at a time this work will be expected to last about 2 weeks, I will keep you updated with the changing schedule. Normal working hours will be M-F 7am – 5pm, however there may be an instance where the pipeline conditioning crew will be working 24hrs for a few days when bringing the gas main into service. I will update with more information the closer we get if this is needed and if any traffic measures will be in place at the time. We will do our best to keep everything flowing smooth and we apologize for the inconvenience. If there’s anything else we can do to help mitigate the effects of the work please reach out.


For more information, please contact the Department of Public Works at 432-2100 or [email protected].



 