2024 Road Program Updates: September 19, 2024
Milling started on 9/17 and will continue through the end of this week. Paving is scheduled to begin on Friday, 9/20. During paving, the roads will be inaccessible to all vehicles. We recommend that during paving, residents park their vehicles outside of the affected roadways. Construction work will begin at 7:00am each day. Roadways will be opened to all traffic at the end of each workday. All scheduling is weather permitting.
See below for updated information.
- Lotus Ln – MILLING COMPLETE. Paving scheduled for Friday, 9/20.
- Elm Ct – MILLING COMPLETE. Paving scheduled for Friday, 9/20.
- Hickory Ln – MILLING COMPLETE. Paving scheduled for Friday, 9/20.
- Sycamore Dr – MILLING COMPLETE. Paving scheduled to begin Friday, 9/20.
- Durante Rd – MILLING COMPLETE
- Gibb Ct – MILLING COMPLETE
- Willow Ct – MILLING COMPLETE
- Cypress Ct – MILLING COMPLETE
- Smithfield Rd & Terr - Milling 9/20
- Chopek Ln - Milling 9/20
- Garabaldi Pl- Milling 9/20 or 9/23 if needed
If you have any questions or concerns, please contact the Borough Administrator’s Office at 201-652-5300 ext. 227.