Road Closures / No Parking due to paving - 5/29-6/6/25

Bethlehem Township's contractor, Recon Construction, will begin the cold-in-place road recycling project May 29, 2025.  This project is weather-dependent, and is tentatively scheduled to end on June 6, 2025.

The schedule is as follows:
  7th St (Wilson Ave to cul-de-sac) - 5/29
  Pheasant Lane - 5/30
  Wilson Ave (7th St to Quarry Dr) - 6/2
  Quarry Drive - 6/3
  Meadow Lane - 6/4
  Sculac Rd (Lehigh Ave to Timothy Ln) - 6/5
  Timothy Lane - 6/6

No parking signs will be posted and residents are asked to park in their driveways or adjacent roadways during paving.

Asphalt recycling is a two-step process:  A base layer is put in place (this coming week).  This base layer will cure for several weeks, and then overlaid with a final asphalt top.

Address/Location
Township of Bethlehem
4225 Easton Ave
Bethlehem, PA 18020

Contact
Emergency: 9-1-1
Non-emergencies: 610-759-2200

Richard Kanaskie
BT Public Works
[email protected]
610-814-6442

TEXT-A-TIP -  Text TIP BETHLEHEMTWP followed by your message, to 888777

Submit an anonymous web tip

Navigate & Discover