City of Oneonta
Thursday May 29th, 2025 :: 10:33 a.m. EDT

Advisory

UPDATE: Market Street Improvements, Phase 2 Transit Hub

Due to last week’s rain events, planting has been rescheduled to begin 6/02/25. This work is expected to be completed end of day, 6/06/25.

Friday 5/30/25, 7:00am there will be a small crew working at the west end of Water St. @ Chestnut St, to saw cut roadway for a required crosswalk.

Monday, 6/02/25  7:00am the roadway west end of Water St. @ Chestnut St. will be removed. When this is completed, trench plates will be installed to allow access into and out of Water Street. 

Monday, 6/09/25 7:00am all access into and out of Water St. will be closed to allow for the placement of required concrete crosswalk.

Tuesday, 6/10/25 7:00am trench plates will be placed over new concrete and Water St. will be re-opened to light vehicle traffic.

Monday, 6/16/25 7:00am trench plates will be removed and Water St. will be re-opened to all traffic.

Sidewalk to Water St. will remain open throughout the duration of this work.

Updates to this PSA will be issued as needed.