SHARON MEWS DRIVE & HIBISCUS LANE REPAIRS
On or about Thursday July 30, road repairs are expected to begin on Sharon Mews Drive.
Work will begin with ADA sidewalk improvements and storm inlet reconstruction. This is expected to take approximately 1 week.
Milling and Paving work will follow on or about Monday August 10. This is expected to take approximately 1 week.
Milling and Paving work on Hibiscus Lane is expected to begin on or about August 6. This is expected to take approximately 2 days.
Residents will have access to their homes throughout the duration of construction. The respective HOAs will be notified as updates become available.