14th Street and Hudson Street reopening Nov. 25; Grand Street restriping begins Nov. 30

14th Street between Washington and Bloomfield Streets to reopen Nov. 25 

The New Jersey Department of Environmental Protection (NJDEP) has announced the reopening of 14th Street between Washington Street and Bloomfield Street in uptown Hoboken at or around 4 p.m. on Wednesday, Nov. 25, ahead of the Thanksgiving holiday.  

The reopening will allow for one lane of vehicular traffic to flow in both directions. The right turning lane on 14th Street will be restored as soon as necessary drainage work is complete.  

The reopening also includes the restoration of the traffic pattern at 15th Street and Washington Street. The temporary traffic light installed at the intersection will be removed Wednesday, Nov. 25, as the traffic light at the intersection of Washington and 14th Streets will be fully operational. 

New Jersey Transit buses will resume their regular route and eliminate the temporary bus stops that were installed on Washington Street between 14th and 15th Streets, and on Willow Avenue north of 15th Street. Buses will resume their regular routes after 4 p.m. on Nov. 25.  

Pedestrian access will be restored to the northern sidewalk on 14th Street between Washington and Bloomfield Streets. The southern sidewalk on 14th Street will be closed for one week in December to perform test pitting. The NJDEP will announce the date of this work in the coming weeks.  

More information about the reopening and the project can be found on the RBDH website: https://dep.nj.gov/floodresilience/rebuild-by-design-hudson-river.  The community liaison can be contacted at 1-800-252-0219.  

For weekly construction schedules, visit www.hobokennj.gov/construction.   

Hudson Street to reopen on Wednesday, Nov. 25 following milling and paving work 

Hudson Street, which is currently closed between Observer Highway and Hudson Place as part of the revitalization of the Hoboken Terminal area, will open to traffic by 4 p.m., Wednesday, Nov. 25.  

The Hudson Place Revitalization Project aims to improve pedestrian and bicycle access, traffic signal improvements, utility upgrades, address area drainage issues, roadway reconstruction, and final paving. 

Grand Street restriping; Parking restrictions announced 

The City of Hoboken will begin striping operations on Grand Street on Monday, Nov. 30. Work will include the removal of delineated parking spaces and the protected bike lane, as well as striping an unprotected bike lane on the east side of the street from Eighth Street to Third Street. 

To complete the restriping work, the City will require temporary no parking restrictions to be in place Monday through Friday, between the hours of 8 a.m. and 4 p.m. The road will be closed intermittently between the hours of 9 a.m. and 4 p.m. Roads will be opened and temporary no parking signs will be removed as work is completed on each block. Local access to driveways will be permitted at the discretion of the Hoboken Police Officers who will be on site monitoring traffic.  

Work is scheduled to begin Monday, Nov. 30, starting at Eighth Street and moving south to Third Street, and is anticipated to last one week.  

Additional information can be found at hobokennj.gov/construction 

 