Christian Brook Sewer Separation Contract 1 - Week of July 5 - July 8

P.Gioioso & Sons will continue work on North Street for the week of July 5th thru July 8th.

Crew #1 will continue installation of the 60-inch drainage piping including ledge removal on North Street between Walnut Street East Back and Beech Street.

Crew #2 (Advanced Drilling & Blasting) will continue drilling and blasting ledge on North Street between Beech Street and Ash Street.

Crew # 2 (Advanced Drilling & Blasting) will start a second crew drilling and blasting ledge on North Street between Russell Street and Hawthorne Street