P.Gioioso & Sons will continue work on North Street for the week of July 11th thru July 15th.
Crew #1 will continue installation of the 60-inch drainage piping on North Street between Walnut Street East Back and Beech Street.
Crew #2 (Advanced Drilling & Blasting) will continue drilling and blasting ledge on North Street between Ash Street and Maple Street.
Crew #3 (Advanced Drilling & Blasting) will continue a second crew drilling and blasting ledge on North Street between Russell Street and Hawthorne Street.