Christian Brook Sewer Separation Contract 1 - Week of September 19 - September 23
P. Gioioso & Sons will continue work on North Street during the week of September 19th thru September 23rd.
Crew #1: Will continue installation of 60” Drain piping on North Street from the Ash Street intersection to Maple Street.
Crew #2: Will continue installation of catch basins on North Street between Russell Street and Hawthorne Street then resume installation of the 12” water main between Russell and Hawthorne.
Crew #3: (Advanced Drilling & Blasting) will continue drilling and blasting ledge on North Street between Ash Street and Maple Street.
In support of the Christian Brook sewer separation project, Liberty Utilities will complete relocating the gas main on Linden Street at the North Street intersection.
If you have any questions, please feel free to contact the project team.
Address/Location
Manchester, NH: City
Manchester, NH 03101
Contact
Emergency: 9-1-1