Christian Brook Sewer Separation Contract 1 - Week of October 31 - November 4
P. Gioioso & Sons will continue installation of drainage and water piping during the week of October 31th thru November 4th
Crew #1: Will resume replacement of the water main on North Street between Hawthorne Street and Ashland Street.
Crew #2: Will complete installation of 42 inch diameter drain piping on Dallaire Street, then begin replacement of the water main on Dallaire Street between North Street and Salmon Street.
In support of the drain piping installation, Liberty Utilities and RH White are scheduled to relocate the gas main on Maple Street at the North Street intersection.