Christian Brook Sewer Separation Contract 1 - Week of December 12 - December 16
P. Gioioso & Sons will continue installation of drainage piping during the week of December 12th thru December 16th .
Crew #1: Will excavate and install Drain Manholes and Catch Basins on Maple Street at the North Street intersection. Maple Street will be closed between Salmon Street and Webster Avenue with traffic detoured to Ash Street.
Crew #2: Will continue installing catch basins on North Street between Hawthorne Street and Dallaire Street and on Dallaire Street.
Crew #3: Advance Drilling and Blasting will continue drilling and blasting ledge on North Street between Maple Street and Oak Street.
In preparation for upcoming work next year, Liberty Utilities and RH White will be relocating the gas mains on Salmon Street and Smyth Road.