Christian Brook Sewer Separation Contract 1 - Week of December 19 - December 23
P. Gioioso & Sons will continue installation of drainage piping during the week of December 19th thru December 23rd.
Crew #1: Will continue to excavate and install 60” diameter Drain piping on North Street between Maple Street and Oak Street.
Crew #2: Will continue hammering ledge and installing catch basins on North Street at Linden Street.
Crew #3: Advance Drilling and Blasting will continue drilling and blasting ledge on North Street between Maple Street and Oak Street.
All excavations will be paved on Thursday, December 22nd in anticipation of the storm on Friday. Minimal work is anticipated to be performed on Friday.
The Contractors will not be working the week of Christmas and the week following New Years. Work will resume on January 9, 2023.
If you have any questions, please feel free to contact the project team.