Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Manchester, NH: City
Tuesday January 17th, 2023 :: 08:00 a.m. EST

Advisory

Christian Brook Sewer Separation Contract 1 - Week of January 16 - January 20

P. Gioioso & Sons will continue installation of drainage piping during the week of January 16th thru January 20th.

Crew #1: Will continue to excavate and install drain piping and catch basins on North Street between Maple Street and Oak Street. The Maple Street detour will remain in effect during working hours.

Crew #2:  Will continue hammering ledge and installing catch basins on North Street. Starting Tuesday the crew will dig test pits to locate utilities on Sagamore and Carnegie Streets.

Crew #3: Advance Drilling and Blasting will resume drilling and blasting ledge on Wednesday on North Street between Oak Street and Hemlock Street.

In support of the project, Liberty Utilities and RH White will complete relocating the gas main on Oak Street at North Street, and continue gas main relocation on Salmon Street and Smyth Road.

Address/Location
Manchester, NH: City

Manchester, NH 03101

Contact
Emergency: 9-1-1

Navigate & Discover