Christian Brook Sewer Separation Contract 1 - Week of March 27 - March 31
Christian Brook Sewer Separation Contract 1 - Week of March 27 - March 31 
P. Gioioso & Sons will continue working in the streets during the week of March 27th thru March 31st.
Crew #1: Will continue excavation and installation of 12” and 48” drain piping and manhole at the North Street and Oak Street intersection.
Crew #2: Will resume casting concrete for drain manhole inverts in North Street
In support of the project, Liberty Utilities and RH White will continue relocation of the gas main on Salmon Street and Smyth Road.
If you have any questions, please feel free to contact the project team.