Advisory
Christian Brook Sewer Separation Contract 1 - Week of April 10 - April 14
Christian Brook Sewer Separation Contract 1 - Week of April 10 - April 14 
P. Gioioso & Sons will continue working in the streets during the week of April 10th thru April 14th .
Crew #1: Will continue excavation and installation of the 24” drain piping on Oak Street at the North Street intersection and installation of catch basins on North Street between Oak Street and Hemlock Street.
In support of the project, Liberty Utilities and RH White will continue relocation of the gas main on Salmon Street and Smyth Road.
If you have any questions, please feel free to contact the project team.