Christian Brook Sewer Separation Contract 1 - Week of April 24 - April 28
P. Gioioso & Sons will continue working in the streets during the week of April 24th thru April 28th.
Crew #1: Will excavate and install the drain manhole and 24” drain pipe at the Russell Street and North Street intersection. Cleanup of equipment and materials along North Street will continue. Installation of catch basins on Oak Street, Hemlock Street and Russell Street will continue.
In support of the project, Liberty Utilities and RH White will continue relocation of the gas main on Salmon Street and Smyth Road.