Christian Brook Sewer Separation Contract 1 - Week of May 1 - May 5
P. Gioioso & Sons will continue working in the streets during the week of May 1st thru May 5th.
The contractor will continue to excavate and install catch basins on North Street near Hemlock and Russell Streets and restore water services to several homes on North Street. Work will continue to install the drain manhole and 24” drain pipe and catch basins on Russell Street at the North Street intersection. Deliveries of drain pipe, manholes and catch basins materials will continue to be delivered and stored near the Russell Street and Smyth Road work zone.
In support of the project, Liberty Utilities and RH White will continue relocation of the gas main on Salmon Street and Smyth Road.
If you have any questions, please feel free to contact the project team.
Address/Location
Manchester, NH: City
Manchester, NH 03101
Contact
Emergency: 9-1-1