Christian Brook Sewer Separation Contract 1 - Week of August 14 - August 18
P. Gioioso & Sons will continue working in the streets the week of August 14th through August 18th .
Crew # 1 will continue to install catch basins on Smyth Road between Salmon Street and Bruce Road. Then will continue installing the main drain pipe and manholes on Smyth Road between Bruce Street and Pickering Street. The crew will also be placing and compacting roadway subgrade gravel on Smyth Road. Smyth Road between Sagamore Street and Pickering Street will be closed to through traffic with detours around the construction zone.
Crew # 2 will work with the subcontractor setting curbs on North Street between Walnut Street and Dallaire Street. Cross street intersections will be intermittently closed to all traffic as the curbs are being set. North Street will have intermittent closures moving with the curb crew.
Tri-State Curb will begin laying curb, starting at Walnut Street and progressing east on North Street.
If you have any questions, please contact the project team.