Christian Brook Sewer Separation Contract 1 - Week of September 11 - September 15
P. Gioioso & Sons will continue working in the streets the week of September 11th through September 15th .
Crew # 1 will continue installing the main drain pipe, catch basins and manholes on Smyth Road between Pickering Street and Kennard Road. The crew will also be placing and compacting roadway subgrade gravel on Smyth Road. Smyth Road between Pickering Street and Kennard Road will be closed to through traffic with detours around the construction zone.
Crew # 2 will continue to prep for curb installation and back up new curbs with concrete on North Street from Maple Street to Dallaire and on Dallaire Street to Salmon Street. North Street and Dallaire Street will have intermittent lane closures moving with the prep and curb crews.
Crew #3 Tri-State Curb will continue to install curbing between Maple Street and Dallaire Street.
The same crews will continue the above activities for the following week from September 18th through September 22nd, with the addition of NHDEP will be performing sewer inspections on Monday, September 18th on North Street.
If you have any questions, please contact the project team.