Christian Brook Sewer Separation Contract 1 - Week of October 23 - October 27
P. Gioioso & Sons will continue working in the streets the week of October 23rd through October 27th.
Crew # 1 will continue installing catch basins on Smyth Road between Pickering Street and Kennard Road. The crew will also be placing and compacting roadway subgrade gravel on Smyth Road. Smyth Road between Belmont Street and Kennard Road will be closed to through traffic with detours around the construction zone.
Crew # 2 will continue to prep for sidewalk installation on North Street from Dallaire Street to Beech Street. North Street will remain open with traffic maintained around the work zones
Crew #3 will continued placement of formwork and rebar and concrete in the underground structure at the installation of Walnut Street and North Street will continue. Both streets will remain open with traffic maintained around the work zones.
Crew # 4: National Water Main will continue preparing manholes on Smyth Road and North Street for anti-scour coatings.
If you have any questions, please contact the project team.
Address/Location
Manchester, NH: City
Manchester, NH 03101
Contact
Emergency: 9-1-1