Manchester, NH: City
Monday November 13th, 2023 :: 10:15 a.m. EST

Advisory

Christian Brook Sewer Separation Contract 1 - Week of November 13 - November 17

P. Gioioso & Sons will continue working in the streets the week of November 13th through November 17th.

 

Crew # 1 will continue placing and compacting roadway subgrade gravel on Smyth Road between Pickering Street and Kennard Road in preparation for paving. Smyth Road between Pickering  Street and Kennard Road will be closed to through traffic with detours around the construction zone.

 

The paving contractor will reclaim, grade and pave Smyth Road between Salmon Street and Webster Ave starting on November 27 and continue through the week. Portions of Salmon Street, Belmont Street, Bruce Road, Pickering Street and Kennard Road will be included in the work zone.  The affected streets will be closed to all traffic with detours around the construction zone.

 

Crew # 2 will mill and pave the intersections of Maple Street and Beech Street at North Street on Thursday, November 16th. Beech Street and Maple Street will be closed to all traffic during paving. Detours will be set up around the construction zone.

 

Crew # 3: National Water Main will start sewer lining on Walnut Street East Back between Salmon Street and North Street and on Dallaire Street between Salmon Street and North Street. The affected roads will be closed to all traffic during lining.

 

If you have any questions, please contact the project team.