Christian Brook Sewer Separation Contract 1 - Week of November 20 - November 22
P. Gioioso & Sons will continue working in the streets the first three days of next week, November 20th through November 22nd . There will be no work on Thursday the 23rd or Friday the 24th .
Crew # 1 will continue paving around structures, driveways and sidewalks and will make improvements to the sidewalk on Smyth Road between Sagamore Street and Kennard Road.
A subcontractor will be working in Salmon Street, Smyth Road and Kennard Road to lower drain, water and sewer structures in preparation for paving the following week.
The paving contractor will reclaim, grade and pave Smyth Road between Salmon Street and Webster Ave starting on November 27 and continuing through the week. Portions of Salmon Street, Belmont Street, Bruce Road, Pickering Street and Kennard Road will be included in the work zone. The affected streets will be closed to all traffic with detours around the construction zone. There will be no parking on the street within the paving area and all residents are encouraged to move their vehicles out of the work zone before paving starts if they see a need to leave during the work.
If you have any questions, please contact the project team.