Christian Brook Sewer Separation Contract 1 - Week of December 11 - December 15

P. Gioioso & Sons and subcontractors will continue working on Smyth Road, Kennard Road and Salmon Street the week of December 11th through December 15th. 

National Water Main will be on Smyth Road and Salmon Street to clean and video inspect the new drain system before it is placed into operation. This is anticipated to take place on Monday. Police details will be with the crew to direct traffic around the work zone.

The final main drain manhole that will redirect the Christian Brook flow from the sewer to the new drain system will be installed. This is a large, deep structure and will require closing Smyth Road between Kennard Road and Pickering Street. This work is anticipated to take the entire week. After the installation is completed, the roadway will be repaved for the winter.

Subcontractors will continue to raise catch basins, manhole structures and gate boxes to finish grade on Kennard and Smyth Roads and Salmon Street. This work will be localized to the immediate work zone and police details will be on site to direct traffic.