Christian Brook Sewer Separation, Contract 2 - Week of January 22 - January 26

Park Construction Corporation will continue work on the sewer separation project for the week of January 22nd  through January 26th .
 
The work will include excavation to install new catch basins on Tory Road between Joe English Lane and Red Coat Lane and temporary paving for the winter.  This block of Tory Road will be closed to through traffic with detours posted around the construction zone.
 
Equipment and materials will be mobilized to North Street for upcoming drain and sewer work between Hall Street and Dallaire Street which will start the following week.
 