Manchester, NH: City
Friday January 26th, 2024 :: 02:00 p.m. EST

Advisory

Christian Brook Sewer Separation, Contract 2 - Week of January 29 - February 2

Park Construction Corporation will continue work on the sewer separation project for the week of January 29nd  through February 2nd .
 
Excavation work on Tory Road between Joe English Lane and Red Coat Lane has been completed for this season, trenches will be paved for the winter this week.
 
The contractor will move equipment and materials to North Street to begin replacement of the sewer and installation of new drain piping and catch basins between Dallaire Street and Hall Street. The affected sections of North Street and Hall Street will be closed, with detours set up around the construction zone.
 
Liberty Utilities and their subcontractor, Feeney Brothers Construction, will continue relocation of the gas main on Oak Street between Webster Avenue and Salmon Street.
 