Christian Brook Sewer Separation, Contract 2 - Week of February 19 - February 23
Park Construction Corporation will continue work on the sewer separation project during the week of February 19th through February 23rd .
Monday, February 19th is a City holiday and no work will be performed that day.
The contractor will start replacement of the sewer piping on Oak Street between North Street and Salmon Street once Liberty Utilities has completed transferring gas services from the old gas main to the new main. This work is anticipated to start mid to late week. During this work, Oak Street will be closed to through traffic on this block with detours set up around the construction zone.
Liberty Utilities and their subcontractor, Feeney Brothers Construction, are scheduled to complete transferring gas services on Oak Street between North Street and Salmon Street.
If you have any questions, please reach out to the project team.
Address/Location
Manchester, NH: City
Manchester, NH 03101
Contact
Emergency: 9-1-1